An electric company with two hydroelectric power plants is for sale. The company has constructed and operated two hydro power plants in Serbia with installed capacity equal to 989kW + 630kW.
The HPP 1 is the run-of-river hydropower plant and is consisted of two water intakes, inlet pipeline and turbine hall with two turbines. The total installed flow rate of HPP, minus the biological minimum, is: Qins = 1600 l/s. All pipeline routes run along water courses mainly in the water land area. In the cases of inaccessible parts of the terrain in locations where the coast is steep, these routes were moved to the other side, where the terrain conditions are more favorable or an AB niche was built so that the pipeline can be placed there.
Tyrolean type water intakes have been chosen as adequate solution and those that can fulfill the purpose and adopted capacities.
This SHPP is a run-of-river type of hydropower plant in which two Francis turbine units have been installed and which is regulated by the level of the upper water.
The HHP 2 is the run-of-river hydropower plant and is consisted of three water intakes, inlet pipeline and turbine hall with two turbines.
The total installed flow, minus the biological minimum, is: Qins = 916 l / s
All pipeline routes run along water courses mainly in the water land area. In the cases of inaccessible parts of the terrain in locations where the coast is steep, these routes were moved to the other side, where the terrain conditions are more favorable or an AB niche was built so that the pipeline can be placed there. Where the pipelines are crossing below the rivers, the pipeline is covered with minimum 25 cm concrete cladding.
Tyrolean type water intakes have been chosen as adequate solution and those that can fulfill the purpose and adopted capacities.
The information in the catalog is not an exact offer. The parameters of the deal are specified during negotiations with the seller.